Scoping the job and walking the site — study guide

The concept's fragments, read in order.

For your capstone Fly a site and deliver a survey-grade map

Every later step of the job answers to the written scope: the mission, the marks on the ground, the accuracy test and the final report. It is where a contractor's sentence about contours and two piles becomes a 16-hectare parcel, 2.5 cm photos, and a 5 cm horizontal and 10 cm vertical accuracy class.

Then the day gets priced, and the flight is the smallest part of it, about 14 minutes in the air. The job has 35 marks, 5 ground control points and 30 checkpoints, with at least three independent measurements of at least 180 seconds each, as the ASPRS field guidance recommends: 35 times 3 times 3 minutes, 315 minutes, 5.25 hours of standing on targets before anyone walks between them. A client who also wants accuracy tested under the trees adds about four and a half hours more.

From a request to a job you can quote

Clients rarely ask for a ground sample distance. They ask for something like "a drone map of the lot before we start grading, with contours, and how much dirt is in those two piles." Scoping is the work of turning that sentence into a specification, much as an architect turns "we want a bigger kitchen" into a drawing with dimensions, materials and a price before anyone picks up a hammer. It settles five things: which deliverables, over what area, at what level of detail, to what accuracy, and with which sensor. Then someone walks the site to see whether the plan survives contact with the ground, and the whole thing is priced in hours.

The decisions come in an order, because each one feeds the next. The deliverables decide the accuracy. Accuracy and detail decide the flying height and how much ground control the job needs. Area and detail decide the photo count and the time in the air. The site itself decides where the aircraft takes off and which corners of the area cannot be mapped the way the client imagines. Change the first answer and every later one moves.

Everything gets written down, because every later step is checked against it: the mission, the marks on the ground, the accuracy test and the final report all answer to the scope. A job without a written scope still ends in a map, but nobody can say whether it is the map that was ordered.

This page works in United States terms: flights under the FAA's rule for small drones, 14 CFR Part 107, accuracy under the ASPRS standard, and coordinates in US datums. Other countries have their own rules and regulators. And the scope sits inside a line each state draws: each state sets where licensed land surveying begins, and where the state reserves them the line can take in topography, contours, volumes and statements of a map's accuracy, not only property lines. This job is done under the responsible charge of a licensed land surveyor, who answers for the control, the accuracy statement and the deliverables, while the pilot plans and flies the mission and processes the data.

What to ask before you quote

Ask what the data is for before asking which products they want. A contractor about to grade a parcel will compare a design surface with the ground as it is now, then move earth until the two agree. That one answer implies a bare-earth elevation model, contours to read it by, and volumes for the material already on site. A client who cannot name an accuracy can almost always name the use, and the use is what decides how good is good enough.

Then pin the deliverables down in the client's own terms. Which files, opened in which software? What contour interval? Which coordinate system and zone, which unit (meters, US survey feet or international feet), grid or ground distances, and which vertical datum, which for this job means NAVD 88? Ask rather than assume. A map delivered in the wrong system lands in the wrong place on the client's screen, and it can look perfect while it does.

Then ask about the ground. Who supplies the boundary of the area, and from what drawing? What date must the data describe, given that stockpiles grow and shrink by the day and the excavators are booked? Are there survey monuments or existing control on or near the site? Who is the site contact, when are the gates open, which other trades and vehicles will be working, and what hazards does the client already know about?

Last, ask what the client does not need. Elevations under the tree line, land beyond the parcel, a property-line survey: each "no" written into the scope is a line that protects both sides when the deliverables arrive.

Turning deliverables into numbers

Client asks for Scope states Field work it fixes Orthomosaic sets 5 cm horizontal class (RMSE) fixes 2.5 cm ground sample distance: fly 300 ft above the ground 1-foot contours sets 10 cm vertical class (RMSE) fixes 30 checkpoints; marks good to 5 cm vertical Two stockpile volumes sets same elevation model, one stated date fixes fly once, before grading; record the date In the ASPRS comparison table, the 10 cm class sits beside a 30 cm (about 1 ft) contour interval
Each deliverable the client asks for is translated into an accuracy class or a stated condition, and each of those fixes a piece of field work: the orthomosaic sets a 5 cm horizontal class and a 2.5 cm ground sample distance flown at 300 ft, the 1-foot contours set a 10 cm vertical class and 30 checkpoints with marks good to 5 cm, and the volumes are tied to one stated flight date.

The ASPRS standard names accuracy by root-mean-square error (RMSE). A "5 cm horizontal accuracy class" means the horizontal RMSE must come out at 5 cm or less; a "10 cm vertical class" means the same for heights. The standard defines an accuracy class as the quality threshold a project's scope of work sets, and it says plainly that it does not endorse ground sample distance, map scale or contour interval as ways to express product accuracy. So the client's words have to be translated into classes before anything else can be planned.

Contours translate through a table. The standard compares its classes with older rules, and under the legacy 1990 rule, in which the allowed RMSE was one third of the contour interval, the 10 cm vertical class sits beside a 30 cm interval, about 1 foot. The grading job's 1-foot contours therefore call for the 10 cm vertical class. The orthomosaic, used to measure features and lay designs over, gets a 5 cm horizontal class. The stockpile volumes come from the same elevation model, so they inherit its vertical quality; how much volume error that means is its own calculation, made later.

Level of detail is ground sample distance. The ASPRS guidance for drone mapping says the minimum acceptable value is usually set by the accuracy the project needs. The job flies at 300 ft (91 m) above ground, under the 400 ft the facility map allows and the 300 ft LAANC approved, for 2.5 cm per pixel, about an inch. Finer is not free: half the pixel size means flying at 150 ft and about four times as many photos to process. Buy the detail the deliverables need, with a margin, and no more.

The classes also fix the field work before anyone sets foot on site. Control and checkpoints must be at least twice as accurate as the product, so good to 2.5 cm horizontally and 5 cm vertically. The standard asks for 30 checkpoints, with their general locations agreed between client and producer as part of the project plan. With RTK camera positions on the aircraft, five ground control points anchor the job. The scope promises the classes and says how they will be tested; the testing itself comes after the map exists.

The area: boundary, buffer and date

The area sounds like the easy part: a square parcel 400 m on a side, 16 hectares or about 40 acres. But the edge of that square has to come from somewhere, and it should come from the client, as a file or a drawing from their own surveyor or their site plans. The pilot maps the area that boundary describes. Deciding where a property line actually runs is boundary surveying, which belongs to a licensed land surveyor, so the scope records where the boundary came from rather than vouching for it.

The area flown is bigger than the area delivered. The ASPRS guidance for drone mapping calls it common practice to cover slightly beyond the project boundary, at least two images before and after the mapping limit along each flight line, and to set ground control toward, if not slightly beyond, the boundary, so the solution is never extrapolating at the edge. On this parcel the flight lines run north and south, so the run-past at the south end of every line, and the turn after it, are over the public road. An observer watches the road and the pilot holds the aircraft short of the edge whenever traffic is coming; on a road too busy for that, the south run-past is dropped. The run-past costs photos as well as ground: the parcel alone takes about 210 photos, and eleven lines run two photos past each end take about 250. On the west side the buffer runs into the tree line, and the scope has to allow for all of that extra ground.

Time is part of the extent too. A stockpile volume is true on the day it was flown and drifts as trucks come and go, so the scope states the date the volumes describe. The bare-earth model before grading is the baseline every later cut and fill will be measured from, so it has to be flown before the machines start moving dirt, not after the first morning of work.

Camera or lidar, and the ground under the trees

west east camera positions ground here never seen lines of sight stop on the canopy open ground: seen from two or more positions low-confidence area, set in advance: no marks, dashed contours, not tested measured ground: control and checkpoints here (triangle), solid contours
Seen in cross-section at the west edge of the parcel, the camera's lines of sight end on the top of the tree canopy, so the ground under the tree line is never seen; that strip is declared a low-confidence area in advance, with no marks in it and dashed contours, while the open ground beside it is measured and tested.

The sensor follows from what has to be measured, and what is standing on top of it. A camera measures only surfaces it can see from two or more positions. On open ground that surface is the ground. Under a canopy it is the top of the leaves, and no amount of processing will find the soil beneath them. Lidar can send some of its pulses through gaps in the canopy to the ground, at a price in cost, weight and complexity.

The grading parcel is open ground and stockpiles with one tree line along its west edge, so a camera on an RTK quadcopter covers nearly everything. The exception is the narrow strip under the trees, and the scope has to say what happens there. The ASPRS standard plans for exactly this. Where photogrammetry cannot see the ground beneath dense vegetation, the producer outlines a low-confidence area, contours through it are drawn dashed, and its extent is documented with the data. Where bare earth is expected to be unlikely or impossible to measure, the standard says to account for the area ahead of time, put no control or checkpoints in it, and leave it out of the accuracy assessment.

That is not the only answer, and the client chooses. If reliable elevations under the trees matter, the standard notes it is common practice to supplement the aerial data with field survey shots there, or the job could switch to lidar. If the client also wants the accuracy under vegetation tested, the standard asks for an additional 30 checkpoints spread through the vegetated area, which at three 180-second readings each is about four and a half more hours on the ground.

Season belongs to the same question. The ASPRS guidance notes that image matching in thin foliage becomes more reliable in leaf-off conditions in fall and winter, and that leaf-off is ideal for lidar too. If grading never reaches under the trees, a dashed strip costs the client nothing; if it does, finding that out now is far cheaper than finding it in the contours.

Walking the site

Parcel 400 m by 400 m, plan view north tree line: note heights; low-confidence strip public road: traffic, wires and poles sight line 566 m (1,860 ft) can the crew see it out here? takeoff and home point, high NE corner, about 226 m phone signal for the RTK network? alternate landing observer watches the road low SW corner, about 212 m marks clear of trees and haul roads
Plan of the 400 m parcel as the site walk sees it: the takeoff and home point sits on open ground near the high northeast corner, away from the tree line on the west edge and the public road on the south edge, and from it the crew must be able to see 566 m (1,860 ft) to the far southwest corner; the walk also checks phone signal, an alternate landing spot, where an observer watches the road, and clear places for the control marks.

Some of the checking happens at a desk. The airspace comes first: this parcel sits inside Class D airspace, the facility map square reads 400 ft, and a LAANC request for 300 ft came back within seconds. At an airport without LAANC, the manual route can take weeks, and that belongs in the schedule before a date is promised. Recent aerial imagery and a terrain map show the slope, the trees and the road. Then someone walks the ground, the way a wedding planner walks the venue a week ahead to find where the cars will park and which door sticks, instead of finding out on the day. The ASPRS guidance for drone mapping recommends exactly this reconnaissance, looking for hazards such as tall objects that may end up dictating the flying height.

Start with access and permission. Who opens the gate, when, and what are the site's own safety rules? Part 107 governs the flight, but where the crew stands and launches is a question of the landowner's permission and of state and local law: the FAA's 2023 fact sheet on state and local regulation lists laws about takeoff and landing locations, where an operator may stand, trespass and land use among those likely to stand alongside federal aviation rules. Privacy laws can apply as well.

Then choose the takeoff and landing spot. On this parcel it is open ground near the high northeast corner, away from both the road and the trees, with an alternate spot picked in case the first is blocked. Stand there and look at the far southwest corner, 566 m (1,860 ft) away. Can the crew keep a small aircraft in sight out there, and does anything stand between? The control link needs the same clear path, since its radio bands work by line of sight. Check the phone signal at the spot too: corrections from an RTK network arrive over the internet, and without a signal the job needs another source of corrections, such as its own base station.

Last, the hazards and the marks. Note the height of the tree line and any wires or poles along the road, since the FAA's guidance names power lines and buildings among the obstacles to look for. Watch how much traffic the road carries, because the south end of every flight line runs out over it: an observer will watch the road so the pilot can hold the aircraft short of the edge whenever traffic is coming, and if the road is too busy for that, the south run-past is dropped. Watch, too, where trucks and workers move on site, which decides where else an observer must look. And look for places where 35 marks can sit for a day undisturbed and visible from above: not under the trees, not in a haul road. These are the same things Part 107 makes the pilot assess before every flight, and the scoping walk finds them early enough to change the plan.

Estimating field and office time

Field time on the grading job, one scale Flight, takeoff to landing: 14 min Occupations on 35 marks: 35 x 3 readings x 180 s = 315 min + walking, laying targets: not counted Only if tested under the trees: 30 more checkpoints, +270 min 0 1 h 2 h 3 h 4 h 5 h Readings per the ASPRS field guidance; flight time from the job's mission plan
Drawn to one time scale, the 14-minute mapping flight is a sliver beside the 315 minutes (5.25 hours) of mark occupations that 35 marks need at three 180-second readings each, before walking and target setting are counted; testing accuracy under the trees would add 30 checkpoints and 270 more minutes.

Estimate from the parts, and expect the flight to be the smallest of them, like a restaurant meal, where the half hour at the table rests on hours of shopping and preparation nobody sees. On the grading job the aircraft is in the air for about 14 minutes from takeoff to landing, on one battery pack, and brings back about 250 photos. Almost everything else in the day is spent on the ground.

The marks set the length of the field day. The job has 35 of them, 5 ground control points and 30 checkpoints, and the ASPRS field guidance recommends at least three independent measurements of each, each at least 180 seconds long. That is 35 times 3 times 3 minutes, or 315 minutes: 5.25 hours of standing still on targets, before anyone has walked between them, laid them out, or checked the rover against a known survey monument. If there is no phone signal for a correction network, a local base station adds its own setup and observing time on top.

The office has two clocks. Machine time grows with the number of photos: one open-source photogrammetry project's documentation lists a minimum of 16 GB of memory for about 250 images and 32 GB for 500, and says to add memory in proportion beyond that, so the job's roughly 250 photos sit right at the 16 GB minimum, and how long they take depends on the machine. Much of the person time goes to orienting the photos and tying them to the ground: a 2020 study of RTK drone mapping called that phase the least automated in the whole workflow, the rest being limited mainly by computing power. At the common convention of marking each target in four or five photos, 35 marks means 140 to 175 careful clicks, before the checking, the contours, the volumes and the report.

The estimate itself is the crew's own rates multiplied by these counts, and those rates come only from timing past jobs. What the counts do show is how the effort scales. Halve the pixel size and the photos roughly quadruple. Test accuracy under the trees and 30 more checkpoints add about four and a half hours of occupations. The quote should move with every one of those requests.

Writing the scope down

The scope ends as a short document both sides agree to before anyone flies. For the grading job it lists the deliverables and their file formats: an orthomosaic, a bare-earth elevation model, 1-foot contours and the volumes of two stockpiles. It names the area by its boundary file and where that came from, the planned ground sample distance of 2.5 cm with the orthomosaic delivered at 3 cm pixels, and the accuracy as classes: 5 cm horizontal and 10 cm vertical RMSE under the ASPRS 2024 standard, tested at 30 independent checkpoints. It names the coordinate systems in full, NAD 83 (2011) State Plane for the site's zone with NAVD 88 elevations from GEOID18, and the unit in words, and it gives the date the data will describe.

Naming the datums is not pedantry. As of late November 2026 NAD 83 and NAVD 88 are still the official US systems. The National Geodetic Survey's replacements have completed their public beta feedback period but have not been approved, and work is delivered in the current systems today. When they are adopted, NGS says every latitude, longitude, ellipsoid height and elevation in the United States will change by as much as about 4 meters, a nationwide ceiling it does not break down by place, with elevations changing by amounts on the order of NAVD 88's own error, about half a meter to two meters against current geoid models. A file labeled only "State Plane, feet" becomes ambiguous the day the new systems are adopted; one labeled with datum, realization, geoid model and foot will not.

Exclusions and assumptions matter as much as deliverables. The strip under the tree line is a low-confidence area, its contours dashed and outside the accuracy test. The work locates no boundaries: no property corners are found or set, and no legal description is written. The scope names the licensed land surveyor in responsible charge, who answers for the control, the accuracy statement and the deliverables. Volumes are as of the flight date. The schedule assumes site access, flyable weather and the airspace authorization for the planned window.

Finally, say what changes the price. More area, elevations under the trees, or finer contours are all new scope. Half-foot (6-inch) contours, for instance, sit beside the 5 cm vertical class in the standard's comparison table, which would likely mean a lower flight, more photos and tighter marks. A vague promise such as "survey grade" gives nobody anything to test; a class, a test and a date do.

The numbers every later step is tested against

Flying a site and delivering a survey-grade map starts here, because this is where "survey-grade" gets a number. For the grading job the scope says: a 16-hectare (40-acre) parcel plus a buffer, an orthomosaic from 2.5 cm photos, delivered at 3 cm pixels, a bare-earth model with 1-foot contours, two stockpile volumes as of the flight date, a 5 cm horizontal and a 10 cm vertical accuracy class, NAD 83 (2011) State Plane coordinates with NAVD 88 elevations, the ground under the trees excluded and marked, no boundary work, and the licensed land surveyor in responsible charge named.

Every later step answers to one of those lines. The mission flies 300 ft above the ground because of the pixel size and the airspace approval. Five control points and 30 checkpoints go where the walk found clear, stable ground. The reported accuracy, which counts the checkpoints' own survey error, comes to 3.5 cm horizontal and 5.2 cm vertical RMSE, inside both classes the scope promised. Stockpile A comes to about 1,400 cubic meters (1,830 cubic yards) and B to about 500 (650 cubic yards), each true for the day it was flown.

Without the scope, none of those results would mean anything, because there would be nothing to hold them against. The accuracy statement would have no target, the volumes no date, the dashed contours no explanation. The survey report at the end of the job largely restates the scope, adding what was measured beside what was promised. A good scope makes that report easy to write and hard to argue with.

Sources

The published studies, standards and guidance this page cites. Links open on other sites.

  1. 14 CFR Part 107, Small Unmanned Aircraft Systems (Electronic Code of Federal Regulations) www.ecfr.gov
  2. ASPRS Positional Accuracy Standards for Digital Geospatial Data, Edition 2, Version 2 (ASPRS, 2024) my.asprs.org
  3. General Statutes Chapter 89C, Engineering and Land Surveying (North Carolina General Assembly) www.ncleg.gov
  4. Professional Land Surveyors' Act, Business and Professions Code 8700 to 8805, as of January 1, 2026 (California BPELSG) www.bpelsg.ca.gov
  5. Part 107 Airspace Authorizations (FAA, page updated October 2026) www.faa.gov
  6. Updated Fact Sheet (2023) on State and Local Regulation of Unmanned Aircraft Systems (FAA and U.S. DOT, 2023) www.faa.gov
  7. Advisory Circular 107-2A, Small Unmanned Aircraft System (Small UAS) (FAA, 2021) www.faa.gov
  8. Installation and Getting Started: Hardware Recommendations (OpenDroneMap documentation) docs.opendronemap.org
  9. Are measured ground control points still required in UAV based large scale mapping? (Teppati Losè et al., ISPRS Archives, 2020) isprs-archives.copernicus.org
  10. New Datums: Replacing NAVD 88 and NAD 83 (NOAA National Geodetic Survey) geodesy.noaa.gov
  11. Track Our Progress, New Datums (NOAA National Geodetic Survey) geodesy.noaa.gov

Next on your path to Fly a site and deliver a survey-grade map: