Contours and volumes — study guide

The concept's fragments, read in order.

For your capstone Fly a site and deliver a survey-grade map

Of everything the job delivers, the 1-foot contours and the two stockpile volumes are what the contractor acts on: the contours become the base drawing for the grading design, and the volumes decide how much fill is on hand and what gets paid for.

Every cubic meter is measured down to a base nobody saw. Suppose stockpile A covers about 700 square meters, 35 m by 20 m, with its long side up the site's average 2.5 percent grade, so its toe falls about 0.9 m. A tilted plane through the toe follows that slope. A level plane at the lowest toe point sits below the real ground almost everywhere, by about 0.43 m on average, and counts roughly 300 cubic meters of the site as pile, more than a fifth of its 1,400. So the base method goes in the report with the volume.

Two things a height grid is for

A bare-earth elevation model answers one question at every point of a site: how high is the ground here. Two of the deliverables a contractor asks for most often are that same answer rearranged. Contours are lines joining points of equal elevation at a fixed interval, such as every foot, and they let a person read slope, drainage and grade off a flat drawing. Volumes are the space between two surfaces, such as the top of a stockpile and the ground under it, or the ground today and the ground as designed.

Neither one adds information. Software threads the contour lines through the grid and sums the volume cell by cell, and both inherit everything the grid got right or wrong. What the operator adds is judgment: which surface the lines come from, how fine an interval the heights can honestly carry, how much smoothing a readable map needs, what surface sits under a pile nobody could see beneath, and how a few centimeters of height error turn into cubic meters of material someone will pay for.

The grading job used throughout is a 16-hectare (40-acre) parcel that rises about 14 m (46 ft) from its low southwest corner to its high northeast corner. The contractor wants 1-foot contours from the bare-earth model and the volumes of two stockpiles of fill. Heights are in the North American Vertical Datum of 1988 (NAVD 88) and accuracy is stated in the terms of the American Society for Photogrammetry and Remote Sensing (ASPRS) standard, which makes this a United States treatment; other countries have their own datums, standards and rules.

Who may produce them is set by each state. Each state sets where licensed land surveying begins, and the line can take in contours and volumes, not only boundaries: the statutes read for this track name determining topography or contours as land surveying, and one state's board puts stockpile volume computations there too. The job this track follows is done under the responsible charge of a licensed land surveyor; a drone pilot's certificate does not reach that work on its own.

Threading a line through the grid

threading the 219 m contour through grid heights (m) 218.6 219.4 219.8 220.2 218.2 218.7 219.3 219.7 217.9 218.3 218.8 219.4 217.5 217.9 218.5 219.1 halfway: 219.0 height above 219 m height below 219 m 219 m crossing, by interpolation crossings joined: the contour worked: 219.0 is 0.4 above 218.6 and 0.4 below 219.4, so the crossing sits halfway between the two points ground rises this way
A 4 by 4 patch of grid heights, each treated as a point at a cell center. Along every line joining two neighboring points where one is below 219 m and the other above, the 219 m crossing is placed by straight-line interpolation, for example exactly halfway between 218.6 and 219.4, and the crossings are joined into the 219 m contour, with higher ground on one side and lower ground on the other.

The software never sees a line. It has a grid of heights, one value per cell, and contouring code commonly treats each value as a point at the center of its cell. To draw the 219 m contour, it looks along each short line joining one cell center to its neighbor. Where one end is below 219 m and the other above, the contour must cross between them, and the crossing is placed by straight-line interpolation: between a point at 218.6 m and one at 219.4 m it sits exactly halfway. The crossings are then joined, cell by cell, into one line. The method is called marching squares, and every contour it produces is the outline of one exact height, like the shoreline water would trace if it rose to exactly that height and stopped.

The interval decides which heights get a line: every whole multiple of it, counted from a base that is normally zero. Every fifth contour is usually drawn heavier and labeled as an index contour, so a reader can count up from it. On the grading job, the ground runs from about 212 m to 226 m, which is 695.5 ft to 741.5 ft. One-foot contours therefore fall at every whole foot from 696 to 741: 46 lines, with index contours at 700, 705 and so on up to 740. The grid's heights must be in the same unit as the interval, or the software will happily draw "1-foot" contours one meter apart.

Contours come from the bare-earth model, never from the surface model. A line threaded through the surface model would climb over the treetops along the west edge and loop around every parked truck, which tells a grading contractor nothing about the ground. And a contour can be no better than the cells it passes through: where the bare-earth model was filled in under objects rather than measured, the line through that patch is drawn from guesses.

The interval the heights can carry

a 5 cm height error, read sideways on a 2.5 percent grade cross-section, heights exaggerated about 18 times 720 ft level 721 ft level ground, in a band of plus or minus 5 cm about 2 m either way where the contour could fall 1-foot contours about 12 m apart 15.2 cm 5.2 cm 15.2 cm: half the 1-foot interval, the 1947 tolerance for 90 percent of heights 5.2 cm: the job's tested vertical RMSE dashed: 1-foot contour levels; dots: where each contour falls with no error
Cross-section of ground rising at about 2.5 percent, with two 1-foot contour levels about 12 m apart. A 5 cm height error is a narrow band around the ground line, but where that band crosses a contour level it spreads the contour about 2 m either way along the ground. The legacy tolerance, half the 1-foot interval or 15.2 cm, is shown beside the job's 5.2 cm vertical RMSE.

Software will draw contours at any interval it is given, one inch if asked, and every one of them will look equally sure of itself. The 2024 ASPRS standard makes the point directly: on digital data the contour interval can be changed with a push of a button without changing the accuracy underneath, so the standard does not endorse contour interval as a measure of accuracy at all. It states vertical accuracy as a root-mean-square error (RMSE) in centimeters. Clients still ask for contours, though, so the standard keeps a translation from two older rules in an appendix.

The 1947 National Map Accuracy Standards said that no more than 10 percent of the elevations tested may be in error by more than half the contour interval. The 1990 ASPRS standard set the RMSE limit for its best class at one third of the interval. Applied to the grading job's 10 cm vertical target, the 1990 rule gives an interval of 30 cm (0.98 ft) and the 1947 rule 32.9 cm (1.08 ft), which is why a 10 cm class is the usual pairing for 1-foot contours; the US Geological Survey built its national lidar program on the same pairing, described as 1-foot equivalent contour accuracy. The job's reported vertical accuracy, which counts the checkpoints' own survey error, is 5.2 cm, comfortably inside. The standard's suggested report wording fits it exactly: elevation data tested to meet 5.2 cm RMSE, using 30 checkpoints in clear, unobscured areas, to support a 1-foot contour interval.

Why the heights must be so much better than the interval shows up on the ground. A contour drawn from uncertain heights is really a band, like a line drawn with a pen whose tip is as wide as the doubt in the heights, so the true edge lies somewhere under the ink, and on gentle ground the band is wide sideways. If the site's 14 m rise ran evenly along its 566 m diagonal, the grade would be about 2.5 percent, 1-foot contours would sit about 12 m apart, and a height error of 5 cm would slide a contour about 2 m across the ground. On flat ground, where a line sits is the least reliable thing about it.

The interval is a promise about the heights, not the drawing. The standard's own warning case is a model built to support 1-foot contours being used to draw 0.25-ft ones: the software obliges, and the extra lines are fiction.

Readable against faithful

Contours threaded straight from a photogrammetric bare-earth model rarely look like a map. Every height carries a little noise, and on gentle ground a little noise is a lot of sideways movement: on the grading site's average grade of about 2.5 percent, a 1 cm wobble in height moves a contour 40 cm. The lines come out crinkled, and tiny closed loops appear wherever a few noisy cells poke above or below a contour level. A US Geological Survey report on generating contours from elevation grids says it flatly: raw contours generally require smoothing before they go on a map.

There are two places to smooth. One is the surface, averaging each cell with its neighbors before contouring; the other is the lines, rounding off their corners afterward. Both move the lines off the surface they were measured from. The same USGS report calls its smoothed contours "not engineering contours" and notes that contours which follow the original surface more closely can be made, but they lose the smoother appearance. That is the whole trade: smoother means more readable and less faithful. A sensible check is to compare a few smoothed lines with the grid's own heights and confirm the shift stays well inside the accuracy being claimed, and that no two lines cross, which contours of a single ground surface never do.

Where the ground was never seen, no amount of smoothing helps. Under the tree line on the west edge, the bare-earth heights are filled in rather than measured. The ASPRS standard asks for such low-confidence areas to be outlined as polygons and reported, calling them the digital equivalent of the dashed contours on older maps, and contours through them, if drawn at all, are dashed.

Smoothed contours are for reading, never for computing. The standard's recommended note on a delivery says the elevation data is the sole source for any further products or computations, so volumes, spot heights and slopes come from the grid, not from the prettier lines drawn on top of it.

Volume as the gap between two surfaces

a volume is a sum of columns between two surfaces solid line: measured pile dashed: base inside the boundary: every column is counted one column: height difference times cell area the job's 5 cm cells: 2 m tall x 0.0025 square meters = 0.005 cubic meters volume = the sum of every column inside the boundary (columns drawn wide for legibility; a real pile has hundreds of thousands)
Cross-section of a stockpile on a base surface, cut into grid columns. Each column's volume is the height difference between the pile surface and the base, times the cell's area, for example 2 m times 0.0025 square meters is 0.005 cubic meters on the job's 5 cm cell, and the volume of the pile is the sum of all the columns inside the boundary.

A volume from a drone survey is never measured directly. It is the space between two surfaces: an upper one that was measured, such as the top of a stockpile, and a lower reference, such as the ground under the pile, a design grade, or the same site surveyed on an earlier day. The software subtracts the lower height from the upper one in every cell, multiplies each difference by the cell's area, and adds up the results inside a boundary drawn around the thing being measured. On the job's grid of 5 cm cells, each cell covers 0.0025 square meters, so a column 2 m tall holds 0.005 cubic meters, and a pile covering 700 square meters is the sum of 280,000 such columns. Software working on triangles instead of square cells does the same thing with prisms.

The method is old and ordinary. North Dakota's transportation department, in its procedure for final earthwork quantities, recommends the surface-to-surface method for borrow, waste and stockpile sites: one surface from a survey of the existing ground, one from a survey of the final ground, and a boundary polygon that must lie inside both surfaces. The procedure says to save that polygon so the calculation can be reproduced, and the software reports cut, fill, the balance between them, and the area. A boundary that strays past the edge of either surface counts columns against nothing.

The grading job's two piles come out at about 1,400 cubic meters for stockpile A and 500 for stockpile B. A US contractor will often think in cubic yards instead, and one cubic yard is about 0.765 cubic meters, so those are about 1,830 and 650 cubic yards.

The arithmetic is trivial for a computer; the judgment is all in the two surfaces. The grid has to be fine enough to follow the crest and the toe of the pile, since the ASPRS standard warns that an accurate point cloud does not by itself give an accurate volume unless the model also represents the shape of the terrain faithfully. And the top of the pile was seen in hundreds of photos, while the bottom was not seen in any.

The ground nobody saw

one pile, three guesses at the ground beneath it ground rises 2.5 percent this way 1. plane tilted through the toe follows an even slope; the base matches the hidden ground 2. level plane at the average toe height misses pile downhill, counts ground uphill; on an even slope they cancel pile missed ground counted 3. level plane at the lowest toe counts ground as pile: about 300 cubic meters under stockpile A ground counted as pile green line: the base used. dotted: the real ground, which nobody saw. shaded green: volume error. heights exaggerated about 3 times.
The same stockpile on ground that rises to the right, with three candidate bases. A plane tilted through the toe follows the even slope. A level plane at the average toe height sits above the real ground downhill and below it uphill, so it misses some pile and counts some ground, and on an even slope the two cancel in total. A level plane at the lowest toe sits below the real ground almost everywhere and counts ground as pile, about 300 cubic meters for stockpile A.

The ground under a stockpile is the one surface a survey of the pile cannot see. A 2019 study of drone stockpile measurement describes the problem plainly: the base is not directly detectable, and unless it is known beforehand it has to be built by interpolating points on the uncovered ground around the pile. In practice the operator traces the toe, the line where the pile meets the ground, and the software builds a base from the heights along that line. Every cubic meter reported is measured down to that invented floor, like finding a load's weight by weighing the loaded truck: the answer is only as good as what you assume the empty truck weighs.

Software usually offers a few kinds of base. The same study lists three planes: one tilted to fit the heights around the toe, one level at the average of those heights, and one level at a height the user types in. A fourth option beats all of them when it exists: a real survey of the ground made before the pile was placed. The tilted and averaged planes suit only piles whose whole toe is visible; a pile pushed against a wall or another pile has part of its toe hidden, and the base has to come from somewhere else.

The choice matters most on a slope. Suppose stockpile A covers about 700 square meters, 35 m long and 20 m wide, with its long side running up the site's average 2.5 percent grade, so the ground falls about 0.9 m from its upper toe to its lower toe. A tilted plane through the toe follows that slope. A level plane at the average toe height is too low on the uphill half and too high on the downhill half; on an even slope the two errors cancel in the total, though not in where the material is. A level plane at the lowest toe point is below the real ground almost everywhere, on average by about 0.43 m, and counts roughly 300 cubic meters of the site itself as stockpile, more than a fifth of the pile.

Real ground is not a plane, and a hump or a hollow buried under the pile is invisible to all three. The study adds that an error in the base height does much more damage to a volume than the same error at the top, because the base error lies under the whole footprint at once. So the base method goes in the report with the volume, the toe is traced on firm ground rather than on loose spill, and a pile that will be measured again is measured against the same base every time.

Cut, fill and the net

Grading a site is the same subtraction with a different pair of surfaces: the ground as it is and the ground as designed, or the ground last month and the ground today. Where the existing ground is above the design, material has to come out, and that is cut, which highway manuals call excavation. Where it is below, material has to go in, and that is fill, or embankment. The software keeps the positive columns and the negative columns apart, so it reports a cut volume, a fill volume, and the net between them, the balance, which tells a contractor whether the site can be graded with its own dirt or needs material hauled in or out.

The two totals and the net do not behave alike. A 2019 study of differenced surveys by a US Geological Survey scientist points out that random height errors push the gross totals of cut and fill up, because every flat patch where nothing changed still shows a scatter of small apparent cuts and fills, while the net is hardly affected by those same random errors. A comparison of two flights over untouched ground is a useful sanity check: whatever cut and fill it reports there is error, not earthwork.

Both surfaces have to describe height the same way. A design in feet against a survey in meters, or a design on one vertical datum against a survey on another, shows up as cut or fill across the entire site. That trap is on its way. As of late November 2026, NAVD 88 is still the official US vertical datum; its replacement, NAPGD2022, has completed its public beta feedback period but has not been approved, and work is delivered in the current system today. When it is adopted, elevations will change by amounts on the order of NAVD 88's own error, which the National Geodetic Survey puts at about half a meter to two meters against current geoid models (a bias of about half a meter and a tilt of about a meter coast to coast). A before survey and an after survey on opposite sides of that switch must be brought onto one datum before they are subtracted.

The volume in the ground is not the volume in the truck. Soil dug from the ground swells into a looser state, and once compacted into fill it usually takes up less room than it did in the ground; a 2023 study for Wisconsin's transportation department measured bank-to-loose expansion in Wisconsin soils of 4 to 8 percent for clean sands and 26 to 58 percent for clays, called for factors specific to each region, and names the loose state as the stockpile state. A drone measures the geometry of the pile as it stands, so the grading job's 1,400 cubic meters in stockpile A is, near enough, a loose volume. Converting it into compacted fill takes a factor from the contractor or a geotechnical engineer, and the deliverable should say which volume it reports.

How height error becomes volume error

height error in the columns, shared or scattered shared shift: every column 5.2 cm too tall the errors stack into one slab under the whole footprint error = area x shift: 700 square meters x 0.052 m = about 36 cubic meters random scatter: each column off by its own amount (cm) +4 -3 +2 -5 +3 -1 +5 -4 +1 -2 highs and lows of the same size mostly cancel in the sum +4 -3 +2 -5 +3 -1 +5 -4 +1 -2 = 0 filled: too tall dashed: too short error heights exaggerated for visibility
The same ten columns twice. When every column is too tall by the same 5.2 cm, the errors stack into a slab, and the volume error is the footprint area times the shift, about 36 cubic meters on a 700 square meter footprint. When the columns are wrong by random amounts up and down, the errors largely cancel and the sum comes out near zero.

A volume is a sum of cells, so the question is how the cells' height errors add up, and the answer depends on what kind of error it is. A shared shift, where a whole surface sits high or low by the same amount, adds a slab as thick as the shift under the entire footprint: volume error equals area times shift, the relation a 2019 study of drone stockpile measurement writes as σV = S × σh. Random scatter, where one cell is a little high and its neighbor a little low, mostly cancels. A USGS scientist's 2019 analysis of differenced surveys puts it plainly: random errors with little or no correlation largely cancel when summed, and the uncertainty of a volume is set instead by the mean error over the area.

Which errors count as shared depends on the two surfaces. Under stockpile A, whose base is built from the same model's heights around the toe, a shift of the whole model lifts the pile and its base together and cancels out. What survives is anything that differs between top and base: a tilt or a gentle dome in the model, a toe traced in the wrong place, and above all the base assumption itself. That is why the base, not the top, dominates a stockpile's error. If stockpile A covers about 700 square meters, an illustrative figure, every centimeter of error in the base is 7 cubic meters, half a percent of the pile, and a base off by the job's whole 5.2 cm vertical RMSE would be 36 cubic meters, 2.6 percent.

Against a design surface or an earlier survey nothing cancels, because the other surface does not share this flight's errors. A 1 cm offset over the whole 16-hectare site is 1,600 cubic meters, more than stockpile A. Two independent surfaces each good to 5.2 cm combine, by root-sum-square, to about 7.4 cm between them. And thin layers suffer most: the same centimeter that is half a percent of a 2 m pile is 5 percent of a 20 cm lift.

Some errors are smaller than they look. A volume computed from State Plane grid coordinates rather than ground distances is off by the square of the combined scale factor; with the example factor of 0.99987, that is 0.026 percent, under half a cubic meter on stockpile A. A volume should go out with its uncertainty, and that uncertainty comes from the base and from any offset between the surfaces, not from the map projection.

The numbers the contractor will pay on

Of everything the grading job delivers, the contours and the volumes are what the contractor will actually act on. The contours become the base drawing for the grading design and its drainage. The stockpile volumes decide how much fill is on hand, how many truckloads move, and what gets paid for. A survey-grade map that ends in a wrong volume has failed at the last step, however good its checkpoints looked.

So these deliverables carry their own statement of how they were made. For the contours: 1-foot interval, threaded from the bare-earth model in NAVD 88 heights from GEOID18, index contours every 5 feet, smoothed for reading, dashed along the tree line where the ground was not seen, and supported by elevation data tested to 5.2 cm RMSE at 30 checkpoints, which the legacy rules translate to an interval of about half a foot, so 1 foot is well within it. For the volumes: stockpile A about 1,400 cubic meters (1,830 cubic yards) and stockpile B about 500 (650), each with its boundary, its base method, the date of the flight, an estimated uncertainty, and the note that these are volumes of the piles as they stand, computed from the elevation grid and not from the contours.

Those notes are what make the numbers checkable. A contractor who disputes a volume can see the base that was used and argue about the base, which is a far more productive argument than one about whether the drone was any good. A volume handed over as a bare number invites the second argument.

Contours and quantities describe the shape of the ground and the material on it; they do not establish where one property ends and the next begins. That does not by itself put them outside surveying: each state sets where licensed land surveying begins, and where the state reserves them the line takes in contours and volumes, so on this job these deliverables go out under the licensed land surveyor in responsible charge.

Sources

The published studies, standards and guidance this page cites. Links open on other sites.

  1. ASPRS Positional Accuracy Standards for Digital Geospatial Data, Edition 2, Version 2 (ASPRS, 2024) my.asprs.org
  2. General Statutes Chapter 89C, Engineering and Land Surveying (North Carolina General Assembly) www.ncleg.gov
  3. Volume Computation Surveys Policy, BP-1007-2 (North Carolina Board of Examiners for Engineers and Surveyors, 2019) www.ncbels.org
  4. gdal_alg.h: GDAL Algorithms C API (GDAL documentation) gdal.org
  5. Creation of Digital Contours That Approach the Characteristics of Cartographic Contours, SIR 2012-5167 (USGS, 2012) pubs.usgs.gov
  6. NDDOT Procedures for Calculating Final Earthwork Quantities (North Dakota DOT, rev. 2013) www.dot.nd.gov
  7. Monitoring and Computation of the Volumes of Stockpiles of Bulk Material by Means of UAV Photogrammetric Surveying (Remote Sensing, 2019) www.mdpi.com
  8. Roadway Design Manual, Chapter Seven: Earthwork (Nebraska DOT, 2022) dot.nebraska.gov
  9. Uncertainty in quantitative analyses of topographic change: Error propagation and the role of thresholding (Earth Surface Processes and Landforms, 2019) pubs.usgs.gov
  10. New Datums: Replacing NAVD 88 and NAD 83 (NOAA National Geodetic Survey) geodesy.noaa.gov
  11. Track Our Progress, New Datums (NOAA National Geodetic Survey) geodesy.noaa.gov
  12. Weight-Volume Relationships and Conversion Factors for Soils and Aggregates of Wisconsin, WHRP G22-05 (WisDOT, 2023) wisconsindot.gov